Project Status
BSA TWIN TOWERS IS NOW 96% COMPLETED!
CONSTRUCTION PROGRESS IS IN FULL SWING!
Major works being done include (but are not limited to) the following scopes:
- • External activities (including exterior masonry, external painting, granite treatment
of the facade)
- • Interior masonry
- • Door jambs
- • Electrical and auxiliary
- • Waterproofing, curtain wall system
- • Drywall partitioning
- • T&B ceiling, floor and wall tiling
- • Elevator activation
- • Installation of kitchen cabinets
- • and the Ground Floor Lobby.
To see more of the construction progress, below are some actual photos of construction
accomplishments.
Main Entrance
The elegant and cozy look of BSA Twin Towers
Main Entrance Lobby and Elevator lobby open
for viewing.
|
|
|
Elevator Lobby
|
Aside from the
Main Entrance at the Ground Floor, construction
progress of our
Lounge Area is also fast moving, now almost complete.
|
|
The Lounge Area already installed with lights, and floor tiles are smoothly done.
|
Moreover, kitchen cabinets were already installed at the units, plus the wall and
ceiling were already painted with its first top coat paint. Floor porcelain tiles
have been completed.
|
|
Kitchen cabinets were neatly installed.
|
As of this date, the percentage of construction accomplishment has reached to
almost 96%, which is still in parallel with its construction schedule.
With this on-going development, expected turn-over of units is ON OR BEFORE
December 2011.